Date Start |
Date Compl. |
Action |
Details |
Responsible Party |
|
4/25/2011 |
5/23/2011 |
Search Committee Established |
See committee roster HERE |
Board |
|
4/30/2011 |
4/30/2011 |
Request for Proposals for Search Firm Issued to 15 Search Firms |
See RFP HERE |
Search Committee |
|
4/30/2011 |
6/10/2011 |
Selected SIMA International based on a review of the 3 proposals received, interviewing the search firms, performing a thorough reference check, and reviewing additional information. |
Recieved proposals from the following firms: Keystone Consulting, Inc., Paideia, Inc., and SIMA International. |
Search Committee |
|
6/13/2011 |
6/13/2011 |
Survey Launched |
|
Search Committee and SIMA |
|
6/29/2011 |
6/29/2011 |
Survey Closed and Results Compiled |
See summary of results HERE |
SIMA Team |
|
6/30/2011 |
6/30/2011 |
Survey Debriefing Call with Santiam |
|
Search Committee and SIMA Team |
|
7/6/2011 |
7/6/2011 |
Santiam Search Committee Meeting and SIMA Introductions |
|
Search Committee and SIMA Team |
|
7/7/2011 |
7/8/2011 |
Interviews with Santiam Community Conducted |
|
SIMA Team |
|
7/8/2011 |
July, 2011 |
Follow up Phone Interviews Scheduled and Conducted |
|
SIMA Team |
|
August, 2011 |
August, 2011 |
Opportunity Profile Developed and Submitted to Search Committee |
|
SIMA Team |
|
August, 2011 |
August, 2011 |
Opportunity Profile Reviewed, Revised, and Approved by Search Committee |
|
Search Committee and SIMA Team |
|
September, 2011 |
September, 2011 |
Opportunity Profile Added to Santiam Website |
See Opportunity Profile HERE |
SC Staff |
|
September, 2011 |
September, 2011 |
Advertising Plan Developed, Approved, and Implemented |
|
Search Committee and SIMA Team |
|
September, 2011 |
October, 2011 |
Critical Requirements Developed, Approved, and Presented |
|
Search Committee and SIMA Team |
|
September, 2011 |
December, 2011 |
Source Candidates |
Progress Reports Provided Monthly |
SIMA Team |
|
December, 2011 |
December, 2011 |
Search Committee Reviews Candidates as they are identified |
|
Search Committee |
|
December, 2011 |
January, 2012 |
SIMA Benchmarking Interview with Narrowed list of 4-5 Viable Candidates |
|
SIMA Team |
|
December, 2011 |
January, 2012 |
Preliminary Reference Checks on Viable Candidates |
|
SIMA Team |
|
January, 2012 |
February, 2012 |
Progress Report to Search Committeee and Further Narrowing of Candidate Pool |
|
SIMA Team |
|
February, 2012 |
February, 2012 |
In-Person Interviews with Semi-Finalist Candidates |
Prepare candidate packages, interview guides, and travel arrangements |
Search Committee and SIMA Team |
|
March, 2012 |
March, 2012 |
SIMA Motivated Abilities Patterns on Finalists |
|
SIMA Team |
|
March, 2012 |
March, 2012 |
Reference Checks and Background Checks on Finalists |
|
Search Committee and SIMA Team |
|
March, 2012 |
March, 2012 |
Second Round of Interviews (if necessary) |
|
Search Committee |
|
April, 2012 |
April, 2012 |
Search Committee to Nominate the next Superintendent of Santiam Christian Schools for Board Approval |
|
Search Committee |